Steel Piles
|

|
Georgia Ports Authority
Bainbridge, GA
Installation of 106, HP14x73 steel H-piles ranging in
length from 57' to 123' for the construction of a new barge terminal. |
|

|
Cape Canaveral Hospital
Cocoa Beach, FL
Installation of 384, 14"Øx.375"
wall, closed-end pipe piles, 128' in length, for the construction of a new
parking garage. |
|

|
Berkman Plaza
Jacksonville, FL Installation of 1,008, 13-5/8"Øx.500"
wall pipe piles. Piles were driven through an existing concrete parking
deck into the St. Johns River below for the construction of a new, urban
residential development. |
|